Debt Outstanding by Project, as of June 30, 2023
| PROJECT | DEBT |
|---|---|
| 1855 Place | 98,449,968 |
| 2019C Savings from Refunding 2010C | (19,035,000) |
| Akers Hall Renovation | 15,938,599 |
| Anthony Hall - Repair simulated slate roof | 85,657 |
| Armstrong & Bryan Hall Renovations | 22,136,823 |
| Auditorium - Alterations to Fairchild Theatre | 9,839,475 |
| Available Proceeds | 1,043,044 |
| Bailey and Rather Halls Renovation | 23,582,647 |
| Bio Engineering Facility | 25,114,211 |
| Biochemistry - HVAC Renovation | 7,219,001 |
| BIOMEDICAL & PHYSICAL SCI BLDG/CHILLER | 2,578,856 |
| Breslin Berkowitz - Facility Upgrades & Hall of History | 550,532 |
| Breslin Bleacher Reconfiguration | 261,882 |
| Breslin Student Events Center - Facility Upgrades | 27,292,585 |
| Broad Business College Complex Pavilion | 19,814,952 |
| Brody Hall Renovations | 34,013,048 |
| Brody utility infrastructure improvements | 835,964 |
| Butterfield Hall Renovation | 11,999,491 |
| Campus Fiber Optic System | 1,842,283 |
| Campus Steam Distribution System | 54,375,510 |
| Cap Interest/Interest Income/Fees/Issuance Costs | (500,277) |
| Case Hall - Elevator replacement | 360,854 |
| Case Hall 1st Floor Renovations of Dining Hall | 14,627,513 |
| Cashier's Office Renovations | 138,035 |
| CEMS Boiler 3 | 165,353 |
| Chemistry - HVAC Renovation | 4,489,565 |
| Chemistry Lab Renovation (5th floor) | 79,963 |
| Chemistry Office Addition | 552,541 |
| Chemistry Office Addition Renovations 2007 | 3,224,091 |
| Chillers 2006 | 1,846,881 |
| Clinical Center C-Wing HVAC | 2,633,053 |
| College of Law | 4,760,442 |
| COMM ARTS PARKING RAMP 5 | 5,132,723 |
| Convert Light T12-T8 | 1,975,773 |
| Cooling Tower 3 & 4 | 330,424 |
| Crescent Middlevale | 1,233,192 |
| Cyclotron Building - Office Addition - Phase III | 10,596,536 |
| Cyclotron Building New High Bay Addition | 3,079,725 |
| Cyclotron Low Eng Exp Res and Off Additions | 12,136,589 |
| Cyclotron Office Addition | 13,319,302 |
| Cyclotron-refrig/cryo projects | 240,023 |
| Data Access in Residential Halls | 515,297 |
| Difference between bond debt service and project repayment schedules | (15,339,187) |
| Duffy Daugherty Football - Renovate Team Locker Room and Training Room | 2,302,902 |
| Duffy Daugherty SAAC - Skandalaris Football Offices and Demmer Hall of History | 2,111,825 |
| EBSP (FIS/HRIS System) | 3,061,676 |
| Electrical Support for Units 5 & 6 | 164,411 |
| Emmons Hall Renovations | 9,965,663 |
| Farm Lane Underpass | 11,635,776 |
| Food Science - HVAC Renovation | 8,323,035 |
| FOOD SERVICE EQUIPMENT UPDATE | 139,687 |
| Food Stores Roof Replacement | 139,997 |
| FRIB 25MW Power Supply | 27,604,639 |
| FRIB Cryogenic Assembly Bldg | 13,191,040 |
| FRIB High Rigidity Spectrometer and Isotope Harvesting Experimental Vault | 23,657,715 |
| FRIB Power Plant Connection | 6,274,324 |
| FRIB Utility Relocation Phase I | 4,929,024 |
| Grand Rapids Property Purchase | 8,438,203 |
| Grand Rapids Research Center | 16,872,797 |
| Grand River Parking Ramp | 10,253,454 |
| Health, Wellness and Fitness Fields at Service Rd | 1,624,975 |
| Health, Wellness, and Fitness Center | 2,726,885 |
| Healthy Campus / Demonstration Hall - Phase 1 - Multi-Use Court Renovations | 1,633,064 |
| Healthy Campus / IM East Gym and Track | 1,559,615 |
| Healthy Campus / IM West Turf Arena Renovations | 3,009,883 |
| HENRY CENTER EXECUTIVE DEVEL. | 265,328 |
| Holden Hall Dining Upgrades | 609,426 |
| Hubbard Hall Asbestos | 113,939 |
| Hubbard Hall Fire Protection | 538,326 |
| HUMAN ECOLOGY SPDC RENOVATION | 1,575,079 |
| HUMAN ECOLOGY SUITE 2 RENOVATION | 267,228 |
| Innovation and Infrastructure Revolving Fund | 500,000,000 |
| Interdisciplinary Science and Technology Building - ISTB | 90,506,668 |
| Jenison Field House | 2,749,117 |
| Kuali Coeus Research Admin | 3,573,822 |
| Landon Renovation | 14,807,620 |
| Low NOX Burner Boilers 1-2 '01 | 531,054 |
| Low Nox Monitoring System | 379,234 |
| Mary Mayo renovations | 7,488,013 |
| McDonel Hall - Electrical Conversion | 155,818 |
| McDonel Hall - Elevator replacements | 333,695 |
| MSU Surplus Store and Recycling Center | 5,258,169 |
| MSU Union Renovation | 503,496 |
| Munn Ice Arena Expansion | 13,273,375 |
| MUSIC BUILDING - ADDITION NO. 3 | 27,964,015 |
| Natural Science Bldg-Window Replc | 1,386,371 |
| Natural Science- New Elect Substation | 683,006 |
| Old Hort Renovations | 413,692 |
| Plant Science Expansion | 36,264,747 |
| Power & Water -- Major repair & replacement (13 projects) | 473,132 |
| Public Art for Debt Funded Projects | 112,370 |
| Regional Chill Water Plant Rpl | 896,235 |
| Replace Chillers - Hannah Bldg. | 484,525 |
| Replace Chillers - Nisbet Bldg. | 175,782 |
| Replace Windows- Human Ecology Bldg. | 224,863 |
| Road- Wilson & Red Cedar - intersection | 1,746,927 |
| Scene Shop Relocation | 374,063 |
| Secchia Center | 76,354,471 |
| Settlement Debt | 370,265,348 |
| Shaw Hall New Dining Center | 9,999,202 |
| Shaw Hall Renovation | 3,628,353 |
| SHAW LANE PARKING RAMP 1 | 8,260,638 |
| SHAW/BOGUE INTERSECTION 2000 | 369,980 |
| SHAW/RED CEDAR INTERSECT 2000 | 349,800 |
| Snyder/Phillips dorm renovation | 20,515,055 |
| South Campus Anaerobic Digester | 2,731,100 |
| Spartan Child Dev Ctr | 1,335,689 |
| Spartan Stadium - Audio Upgrades | 1,181,332 |
| Spartan Stadium - North and East Bowl Restoration | 1,333,029 |
| Spartan Stadium North End Zone Addition | 1,840,110 |
| Spartan Turf Paved Nursery | 309,751 |
| Spartan Village - Re-roof various bldgs | 214,782 |
| Spartan Village Electrical | 968,080 |
| SRF High Bay Addition Phase I | 11,766,807 |
| Stadium Column Repair 2000 | 873,051 |
| Stadium Column Restoration | 303,333 |
| Stadium Expansion | 30,554,713 |
| STADIUM NEW TURF | 793,870 |
| Stadium North Restoration '02 | 810,856 |
| Stadium Restoration of East Stands 2000 | 2,085,094 |
| Stadium South Stands | 441,833 |
| Stadium W. Concourse & Columns | 489,966 |
| STEM Teaching and Learning Facility | 62,409,722 |
| STEM Teaching and Learning Facility - Shaw Lane Power Plant | 6,120,823 |
| Stm Dist & Road Rec E/W Circle Drive | 6,223,935 |
| Stores Addition | 209,317 |
| Student Data Service | 509,481 |
| T.B. Simon Power Plant - Modernization - Boilers | 17,175,642 |
| T.B. Simon Power Plant - Modernization - Reverse Osmosis | 62,065 |
| T.B. Simon Power Plant - Modernization - RICE | 44,371,463 |
| T.B. Simon Power Plant - Modernization - RO system | 62,264 |
| T.B. Simon Power Plant - Upgrade Utility Substation | 22,112,596 |
| TB Simon Dem Storage Tank #2 | 222,858 |
| TB Simon Low NOx Burner Installation #3 Boiler | 415,659 |
| TB Simon Power Plant - Coal Handling Changes Phase I | 15,079,417 |
| TB Simon Power plant addition | 20,037,083 |
| TB Simon Power Plant SNCR 1,2,3 | 1,412,557 |
| Track & Field Turf | 1,608,896 |
| Union Mechanical Renovation | 566,299 |
| University Village | 9,118,054 |
| Utility Distribution -- New elec. sub. sta. for Owen Graduate Center | 274,958 |
| Vet. Med. Center - Replace deteriorated roofs | 148,773 |
| Veterinary Oncology | 279,544 |
| Water Distribution - Campus Water System Improvements | 17,727,930 |
| Wells Hall Addition | 29,306,360 |
| Wharton Center Expansion | 11,106,926 |
| Wilson Hall - Electrical Conversion | 185,341 |
| Wilson Hall Alterations (C-102 Auditorium) | 132,360 |
| Wilson Rd Phase 2 | 1,493,174 |
| Wonders Hall - Teaching, Learning, and Student Support Renovation | 11,430,597 |
| Grand Total | 2,104,868,000 |